Procurement of Heathrow T5
Contents |
[edit] Introduction
Megaproject clients are often disappointed with the outcome of their project, be it over budget, delayed or not to the specification they requested at tender stage.
This article investigates the procurement systems, culture and trust issues that the key stakeholders had to contend with during the £4.3 billion construction of Heathrow Terminal 5. The results reveal that the success of the project was dependent upon the culture of trust and the approach to risk adopted by BAA during the procurement process. It is recommended that the steps implemented by BAA should be replicated in future megaprojects.
[edit] Background
On 27 March 2008 Heathrow Terminal 5 (T5) opened after approximately 19 years of planning and £4.3 billion investment by British Airport Authority (BAA). Laing O’Rourke, AMEC and MACE were the three principal contractors employed, although as highlighted by Basu (Little and Millard, 2009) by 2008 fifty thousand people, employees and key stakeholders had been involved in the construction.
Ryan Donnelly who was the chief engineer for the T5 project concluded with BAA suggestions that an alternative procurement method was required to meet the project objectives and deliver the project on time and within budget. Prior to construction BAA conducted a two year study in which ‘every major UK construction project of over £1bn conducted over the previous 10 years and every international airport that opened over the previous 15 years’ (Brady and Davies, 2009) were investigated. Brady and Davies (2009) discussed the findings, stating that of those investigated none had been constructed on time, within budget and to the original standard set out. Davies (Gann and Douglas, 2009) echoed Brady and Davies (2009) discussions noting it would be £1 billion over budget, over a year late and with at least two fatalities.
However, the study predictions were not fulfilled. T5 was completed on time and within budget (later complications regarding the roof may divide opinion as to the overall success of the budget).
This article will discuss the reasons behind the success of the project, focussing on three commercial management issues identified by Lowe and Leiringer (2006) namely; procurement systems, culture and trust. The commercial management issues will be evaluated and the commercial legacy for future projects highlighted.
[edit] Procurement Systems
A range of different procurement systems exist to source the labour, plant and materials required to construct a building. Clients will generally be advised by an architect, project manager, quantity surveyor or another related professional on the most appropriate procurement route depending on project size, complexity, cost and risk.
The procurement system adopted by an inexperienced client will often be based purely on the recommendations of the professional initially appointed. However research by Ireland (1989, cited by Langford and Murray, 2006) into six procurement methods concluded that those investigated had ‘virtually meaningless distinctions.’ Hibberd and Djebarni (1996, cited in Langford and Murray, 2006) found most clients and consultants, were unhappy with their procurement system, most likely having been ‘seduced by the comfort of options’ without fully evaluating the selected merits. Further discussions of Hibberd and Djebarni (1996 cited in Langford and Murray, 2006) found that commercial gain was a significant factor in promoting the options but often that benefit is not passed to the client. These findings would imply that experienced clients base their chosen method on systems they know, but previous issues increase the likelihood that they will seek new options.
An important outcome of procurement is ‘value’, the meaning of which varies between people and organisations. Some view value as lowest price, while others look to get a mix between quality and cost. Langford and Murray (2006) highlighted the different perspectives of value, including ‘economic, marketing and business’ concluding that ‘value in procurement is a social and political construct as well as being bounded by economic selectivity’. Ultimately the strategy for procuring value will be limited by the economic boundary i.e. one must buy within ones’ means. However, the product selection of the options within this boundary will depend on the organisational culture on what constitutes value; within T5 the culture was changed from the traditional and this will be discussed later.
The procurement within T5 was discussed by Caldwell (Roehrich and Davies, 2009) noting that BAA’s intention from the start was to have a few close relationships with pre-selected supply partners through the T5 agreement. This would lend itself towards achieving the ‘value’ approach of attaining quality, rather than ‘lowest price wins’. Close relationships were formed upon the basis of trust, and this was important in ensuring value from the selected procurement route.
Both Brady and Davies (2009) and Davies (Gann and Douglas, 2009) commented on the two areas identified by BAA which contributed to the previous poor performances, namely, a lack of collaboration among project partners and the client’s reluctance to assume responsibility for project risk. BAA’s response to the findings was to “change the rules of the game” through the management and commercial structure. This “rule change” was achieved by adopting a partnering approach to procurement.
Wolstenholme (2008) noted the procurement strategy adopted was in direct response to the assessed risk that the project posed to BAA as a business. In order for the project to be successful and targets met, BAA introduced a new procurement strategy based upon the partnering approach. The most likely catalyst for the unique contractual approach came from BAA’s CEO Egan. The T5 agreement ‘employed the same philosophy applied by Egan when he produced Rethinking Construction.’ (Williams, 2008)
Partnering encourages parties to embrace trusting and cooperative relationships. Sir John Eagan (at the time of T5 he was BAA’s CEO); in Rethinking Construction, redefined the term partnering to ‘supply chain management’ introducing principles from manufacturing to ensure success. Partnering was by no means without critics, Green (1999, as cited in Fellows, 2006) went so far as to note that the idea had ‘become dangerously radical by replacing the central tenants of a regulated market economy with an ideology uncomfortably close to naked corporatism.’ Success in partnering is centred on trusting relationships. Therefore the trust instilled as part of the T5 culture was paramount to its success.
Commonly risk is transferred down the supply chain though the use of the procurement system. Rowlinson and Kvan (2004) described this approach as ‘vicious circles in the procurement process’ whereby the supplier with the least financial stability bears all the risk. The construction industry is founded on subcontracted labour from small firms. The transfer of risk to the small firms can often lead to their demise, in turn undermining the structure of the industry. BAA addressed this risk transfer at T5, and their commercial success provides a risk legacy which should be considered again.
A contractor views risk as a cost or an opportunity. If the risk arises, it is an additional cost, but, if it does not, their risk contingency becomes profit. Traditionally clients will try and transfer risk to contractors. Contractors will therefore price it within their tender and will in turn try to pass on the risk to their subcontractors. BAA took a different and unique approach to risk in T5 – they held all the risk - deciding it would be ‘the best way to achieve price certainty.’ (Focus on Transport, 2007) Subsequently the contractors risk contingency was removed, lowering the overall tenders. Obviously with no risk placed on the contractor, incentives were required to encourage all to work to minimise the risk – the approach of ‘it doesn’t matter, it’s not my bill’ had to be avoided for this scheme to be successful. The risk was managed through financial incentives for suppliers, rewarding successful performances. During the design stage the risk contingency was held within each project, however in 2004 Bullock decided cost targets could be more challenging. This resulted in £100 million taken from individual projects to a central pot which allowed the risk contingency to be allocated depending on where it was needed (Doherty, 2008). This contingency allowed greater control of the financial implications of risk at a more global level and thus tighter overall budget control.
Even prior to the completion of T5 the commercial legacy of the partnering approach was being adopted by Laing O’Rourke in the Channel Tunnel Rail Link terminal at St. Pancreas. Although the risk approach which had been adopted by BAA was not being used, as Davies (Gann and Douglas, 2009) discussed, the T5 approach was reused for the target cost “pain/gain share” principle.
[edit] Culture
Many definitions of culture definitions exist; Hofstede (1994) defines it as ‘the collective programming of the mind which distinguishes one category of people from another.’ However, a more succinct definition of culture within an organisation from Fellows (2006) is ‘how we do things here.’
Culture exists within an organisation. It is ingrained and makes change difficult, and consequently change will only occur over a long period rather than quickly. A climate also exists within an organisation and can be changed in a relatively short period. However, its ability to change is also a weakness, as both negative and positive climates can infiltrate an organisation. The climate is the surface of the organisation and the culture underlies this and will remain constant even with fluctuating climate changes. Both culture and climate are subject to change because of power influences.
The core layer of culture is often said to be values, then beliefs and ultimately is manifested through the behaviours displayed by individuals. One of the core values within T5 was teamwork. This was encouraged through the passing of a rock upon a completed milestone. This ceremonial handover, may seem trivial, but was done with great pride and the teamwork culture within the project meant workers did not want to let the team down by passing the rock late (Doherty, 2008).
The construction industry involves individual projects such as T5. Fellows (2006) states these individual projects are often referred to as ‘temporary multi-organisation (TMO) involving individuals from varying power based coalitions. These TMO’s may display the culture of the organisation, but their climate will vary in line with the objectives of those in power.
Within T5, BAA sought to create a new culture which encouraged people to:
- Seek out, capture and exploit the best practices of others.
- Remove the barriers and inhibitors to doing things differently.
- Stimulate and support good ideas.
- Leverage the commercial incentive to perform exceptionally (Wolstenholme, Fugeman and Hammond, 2008).
Partnering and other similar procurement methods must have a different climate compared to that of traditional and design and build methods, as the feeling of trust and cooperation is key to the success. With traditional procurement methods arguably trust and cooperation would improve the performance and satisfaction of all parties involved, although they are not essential to ensure success.
The T5 agreement was a cost-plus contract (the client pays the suppliers actual cost plus a fixed fee which includes overheads and profit) based upon a partnering approach. Caldwell (Roehrich and Davies, 2009) highlighted that the T5 agreement was based upon behaviours and relationships, allowing ‘bespoke’ interactions between BAA and suppliers. Doherty (2008) discussed how the contractors involved within the project mentioned previous ‘games’ that they used with more traditional contracts, such as bidding low to win the project and then working to commercially protect their company during the project. The approach adopted within T5 discouraged these methods by adopting fair payment practices and changing the culture within the project. The culture literature reviewed highlights that the success of this contract was dependent upon the culture within the project. BAA instilled a culture with reduced emphasis on contractual principles commonly observed in construction, and promoted a behavioural focus. The reduction in contract focus allowed an informal approach, in turn reducing the contractual conflict commonly reported. A goal sharing rather than individual goal culture was adopted within T5. It is important to highlight the informal approach was potentially only possible due to BAA bearing all the risk, and therefore for this culture change to have future commercial impact, arguably clients must assess risks and look to manage them themselves.
Davis Langdon (2010) report partnering only accounts for 1% of procurement methods chosen and so it is no surprise that the companies working on T5 experienced a culture shock when they first started. Davies (Gann and Douglas, 2009) discussed the culture “shock” that Laing O’Rourke experienced during the T5 construction. Laing O’Rourke a traditional contractor had to quickly learn to adapt to the BAA partnership employed.
[edit] Trust
Wood and McDermott (1999) defined trust as ‘a willingness to rely on the actions of others, to be dependent upon them, and thus be vulnerable to their actions.’
Malik et al (2007) investigated the notion of trust through a series of interviews, and found that the majority of those interviewed agreed that ‘trust was concerned with the way people communicated with each other.’ It is important that clear communications exist in order for information sharing so problems can be solved. This was particularly important within the risk conundrum, where in order for risk to be avoided communications between parties must be good, so all are informed of potential problems. The freedom of communication and the ability for people to speak without fear of blame was essential to the success and it was the trusting nature instilled within the community that provided this.
The procurement system adopted was based upon the partnering approach. In order for this to be successful, trusting relationships between parties must be established. The payment mechanisms were based on a cost plus approach with open book philosophies, agreed profit margins ensuring all parties were satisfied and the project was completed within budget. It was important all parties trusted that a fair analysis of work done would be conducted. The whole commercial process was partnering in its purest form with a totally open book approach. Trust was therefore essential between BAA and all involved to ensure all parties were content.
The culture established within the project was a trusting culture whereby individuals were selected upon merit rather than the organisation they worked for. It was important for managers to be able to trust those within their team, some of whom they may have met only briefly, rather than having had a long term relationship. Malik et al (2007) found that trust was not isolated to one situation, but built up over time. It is therefore a success of T5 that trust between parties was established in such a short space of time.
Arguably it was the formation of trust from contract mechanisms that enabled the success of T5; ‘the formation of integrated teams and the application of a novel form of contract enabled trust between all parties to be established.’ Wolstenholme (2008) noticed BAA’s project strategy, where they acknowledged the significance of risk in establishing trust. Their decision to shoulder all risk left one less excuse for distrust by removing the vulnerability which people and organisations would have otherwise had to bear. Trust is built upon the sharing of information, and the reliance on this information, Bigley and Pearce (1998, cited in Malik et al, 2007) reiterated this, stating ‘there is also an element of reliance.’ BAA’s shouldering of the risk, required all to work together to negate the risk. To achieve this, individuals had to rely on the information given to them, in order to make the correct informed decision which would produce the most effective way of preventing, reducing or managing the risk.
[edit] Conclusion
In conclusion, if BAA had not conducted a two year study to understand the fundamental problems that have plagued previous mega projects the outcome of this project would most likely have been as predicted; approximately £1billion over budget, more than one fatality and at least a year late.
[edit] Related articles on Designing Buildings Wiki
- Airports National Policy statement and Heathrow.
- Airports.
- Balanced scorecard.
- Collaborative practices.
- Cost plus contract.
- Egan Report.
- Framework agreement.
- Gatwick second runway.
- Heathrow Airport expansion.
- Heathrow Terminal 5.
- Thames estuary hub airport.
- Integrated project team.
- Integrated supply team.
- Latham Report.
- Partnering.
- Procurement route.
- Sustainability of Heathrow 2.0.
[edit] External references
- 1. Basu, R., Little, C. and Millard, C. 2009. Case Study: A Fresh Approach of the Balanced Scorecard in the Heathrow Terminal 5 Project. Measuring Business Excellence, vol. 13, no. 4,
- 2. Brady, T. and Davies, A. 2009. From Hero to Hubris – Reconsidering the Project Management of Heathrow’s Terminal 5. International Journal of Project Management, vol. 28, no. 2,
- 3. Caldwell, N.D., Roehrich, J.K. and Davies, A.C. 2009. Procuring Complex Performance in Construction: London Heathrow Terminal 5 and a Private Finance Initiative Hospital. Journal of Purchasing and Supply Management, vol. 15, no. 3,
- 4. Davies, A., Gann, D. and Douglas, T. 2009. Innovation in Megaprojects: Systems Integration at London Heathrow Terminal 5. California Management Review, vol. 51, no.2
- 5. Davis Langdon. 2010 Contracts In Use: A Survey of Building Contracts in Use during 2010.
- 6. Doherty, S. 2008 Heathrow’s Terminal 5: History in the Making. Chichester: John Wiley & Sons Ltd
- 7. Fellows, R., 2006. Culture. In: Lowe, D. & Leiringer.R., 2006, Commercial Management of Projects Defining the Discipline. Oxford: Blackwell Publishing. Ch.3.
- 8. Hofstede, G.H. 1980. Culture’s consequences: International Differences in Work-related Values. Sage, Beveley Hills, CA.
- 9. Hofstede, G.H. (1994a) The business of international business is culture. International Business Review, vol.3, no.1
- 10. Hofstede, G.H. (1994b) Cultures and organizations: Software of the Mind. Harper Collins, London.
- 11. Langford, D. Murray, M. 2006. Procurement in the Context of Commercial Management. In: Lowe, D. & Leiringer.R., 2006, Commercial Management of Projects Defining the Discipline. Oxford: Blackwell Publishing. Ch.4.
- 12. Lowe, D. & Leiringer.R., 2006, Commercial Management of Projects Defining the Discipline. Oxford: Blackwell Publishing.
- 13. Malik M.A. Khalfan, McDermott, P. & Swan, W. Building trust in construction projects, Supply Chain Management: An International Journal, vol. 12, no. 6
- 14. Public Private Finance, 2007. Focus on Transport: That’s the way to do it: Heathrow’s Terminal Five is a role model for the Industry. Available through: Loughborough University Library Website [Accessed 14 November 2012]
- 15. Rowlinson, S and Kvan, T. 2004 Procurement Systems. In: Langford, D and Murray, M., 2004, Architect’s Handbook of Construction Project Management. London: RIBA Enterprises. pp141-157.
- 16. Williams, R. 2008. The perfect storm: Underwriting the construction of Heathrow Terminal 5. Gleneagles, 16 September 2008. Swiss Reinsurance Company Limited
- 17. Wolstenholme, A. Introduction. Proceedings of the ICE - Civil Engineering, vol. 161, no. 5.
- 18. Wolstenholme, A., Fugeman, I. and Hammond, F. Heathrow Terminal 5: Delivery Strategy. Proceedings of the ICE - Civil Engineering, vol. 161, no. 5.
- 19. Wood, G., McDermott, P. 1999. Looking for trust in construction: an interim view. In: Ogunlana, S.O., 1957- 1999, Profitable partnering in construction procurement. CIB W92 (procurement systems) and CIB TG 23 (culture in construction) : joint symposium, London : E&FN Spon, London.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments